Walk west on Main Street after a Thursday night show at the Stephen Talkhouse this month and you will feel the new brick under your shoes before you see it. The stretch between Hedges Lane and the western entrance to Amagansett Square used to be a worn strip of grass, the kind that gives way to bare dirt by August from years of foot traffic. Now it is brick, laid flush with a widened sidewalk, matching the pattern that has lined the north side of Main Street for years. It reads finished, deliberate, done.

Look up, though, and the light falling on that new brick is coming from the same sodium-orange cobra-head fixture that has hung over Main Street for decades. The historic-style streetlights that were supposed to replace it, warmer, lower, styled after the ones in Sag Harbor, are still sitting in committee. The sidewalk got built. The lighting did not. And the gap between those two outcomes says more about how Amagansett actually gets things done than either project does on its own.

One Complaint, Two Timelines

Both projects trace back to the same underlying concern: Main Street is a state highway running through a historic hamlet with old trees, narrow shoulders, and heavy summer foot traffic, and it has not always been safe to walk. Attendees at a 2025 committee meeting on the lighting plan cited two pedestrian deaths on Main Street over the years, including the hit-and-run death of John Judge in October 2012, as the reason the streetlight conversation started in the first place, according to reporting from The East Hampton Star. Rona Klopman, chairwoman of the Amagansett Citizens Advisory Committee, told the town board back in 2024 that the lighting project had existed as "only a vision" for more than seven years.

Somewhere along the way, that single safety concern split into two separate town projects with two very different paths to completion.

Project First formally proposed Estimated cost Who pays Status as of this fall
South-side brick sidewalk Debated by the town board in March 2026 Not separately itemized; covered by a state grant State grant Substantially complete ahead of Memorial Day 2026
Historic-style streetlights Presented to the town board in November 2024 (origins date to roughly 2017-2018) About $1.3 million, all in Amagansett Main Street tax district, not townwide Still being priced for a board vote as of June 2026, no installation date set

The sidewalk moved in months. The lighting has moved in years, and it is still moving.

What Got Poured

The sidewalk debate itself was almost quaint by comparison. At a March 2026 meeting, the choice on the table was literally grass or brick, according to the Star's coverage. Councilman David Lys, who brought the design forward, argued for widening the walk from four feet to five and paving the worn median in brick.

"Let's be honest: Amagansett is happening right now."

That was Lys's pitch to the board, reported by 27east.com. His point was practical rather than aesthetic. The old four-foot sidewalk could not handle two people walking side by side without one stepping into the road, and the grass strip meant to buffer pedestrians from traffic had been trampled into hardpack years ago.

Councilwoman Cate Rogers pushed back on one detail, not the brick itself but what would replace it if brick lost out. "Brick is something that fits in with the historic nature, and I would hate to see concrete all the way to the curb as a replacement," she said, adding that concrete would "take that small town feeling away that we all love so much and is why we live here." Councilman Tom Flight, the town board's Amagansett liaison, noted that grass was never going to hold up anyway, since the tree canopy over Main Street blocks too much summer light for it to grow back reliably.

Brick won. The town wrapped the work in time for Memorial Day, boxing the mature trees along the route in six-by-six-foot planters to protect their roots during construction. Today, if you walk that stretch from Amber Waves Farm past Amagansett Square and on toward the west end shops, the surface under your feet is continuous for the first time in years.

What's Still Wearing a Cobra Head

The lighting story has not resolved nearly as cleanly. A November 2025 meeting of the Amagansett Citizens Advisory Committee spent nearly an hour on it, with engineer Matt Jedlicka of L.K. McLean Associates presenting a plan that closely tracked the one his firm had shown the town board a year earlier: 46 to 50 historic-style fixtures, spaced roughly 100 feet apart, running from Windmill Lane to Meeting House Lane, replacing the existing cobra-head lights on their tall metal poles.

One detail from that meeting is worth knowing if you were at the Talkhouse in August of last year. Consulting on the lighting design was John Broderick, a lighting and production designer who has worked extensively with Metallica, the band that had played a sold-out show at the Talkhouse the previous summer, drawing thousands to the hamlet and, by the Star's account, "more than a little annoyance" from some committee members dealing with the crowds. Broderick found himself defending the plan against resident Dan Mongan, a trustee of both the Amagansett Library and the Amagansett Historical Association, who raised concerns that the new fixtures would spill light onto private Main Street properties. Broderick countered that the design was targeted enough to avoid meaningful trespass, while another committee member warned that overdoing it could permanently alter the character of a designated historic district.

The project has also been slowed by the fact that Main Street is a state highway, which means any change requires sign-off from the New York State Department of Transportation. An earlier idea to bury the utility lines alongside the new lights was explored and then dropped after coordination with PSEG Long Island and Verizon proved too complex, refocusing the project back on its original, narrower goal of safety lighting.

As of the town's June 2026 update, delivered by Councilman Flight during his regular liaison report, the board had received fresh cost estimates and Flight said he would bring them to his colleagues "next month." No vote followed that made headlines, and no installation date has been announced since. In that same report, Flight mentioned that the crosswalk signal on Main Street, which had been flashing without pause for months, would be fixed once replacement parts arrived, likely within six weeks. Small detail, same pattern: the visible, physical fixes move. The parts-and-committee fixes wait.

Why the Gap Is Worth Noticing This Month

None of this is abstract if you are actually out on Main Street this fall. Rowdy Hall's Oktoberfest specials run from September 19 through October 4 this year, with an expanded beer garden and outdoor bar that will keep people outside well after sunset, according to Dan's Papers. The Talkhouse has shows most nights through the end of the month. The Amagansett Square farmers market runs Thursday afternoons from 3:30 to 6 p.m. through the end of September, and the smaller Wednesday market at the Amagansett Historical Association, on the lawn at 129 Main Street, keeps its own quieter schedule into the fall. Every one of these puts people walking Main Street in the exact hours when the difference between a new streetlight and an old cobra head would actually register.

The brick sidewalk makes that walk more comfortable during the day, when the sun does the work the streetlights would otherwise be doing. Once the days get shorter, and September in Amagansett gets dark by early evening, the sidewalk's finish stops being the relevant fact and the overhead light becomes the one that matters.

If you want to track where the lighting project actually stands, the Amagansett Citizens Advisory Committee meets regularly and its discussions get folded into the town board's public liaison reports. It is a slower way to follow a story than checking a restaurant's Instagram for its Oktoberfest hours, but it is the only way to know when the second half of this project finally catches up to the first.

For those who live here year-round, or who are weighing what it means to spend more of the year in a place like this, the small, unglamorous infrastructure decisions tend to say as much about a hamlet's character as its restaurants do. Deborah Srb has spent more than three decades paying attention to exactly this kind of detail across Amagansett and the rest of the South Fork. If you would like a conversation about what's changing on the ground here, in more ways than one, Work With Deborah.

Work With Deborah

Work With Deborah

Deborah Srb, a Sotheby’s International Realty agent, is a skilled professional with insightful local knowledge and extensive expertise in Hamptons luxury real estate.

Follow Me on Instagram